20楼#
发布于:2012-02-02 17:08
19. It is only those obligations arising from past events existing independently of an enterprise's future actions (i.e. the future conduct of its business) that are recognised as provisions. Examples of such obligations are penalties or clean-up costs for unlawful environmental damage, both of which would lead to an outflow of resources embodying economic benefits in settlement regardless of the future actions of the enterprise. Similarly, an enterprise recognises a provision for the decommissioning costs of an oil installation or a nuclear power station to the extent that the enterprise is obliged to rectify damage already caused. In contrast, because of commercial pressures or legal requirements, an enterprise may intend or need to carry out expenditure to operate in a particular way in the future (for example, by fitting smoke filters in a certain type of factory). Because the enterprise can avoid the future expenditure by its future actions, for example by changing its method of operation, it has no present obligation for that future expenditure and no provision is recognised.
21楼#
发布于:2012-02-02 17:08
20. An obligation always involves another party to whom the obligation is owed. It is not necessary, however, to know the identity of the party to whom the obligation is owed - indeed the obligation may be to the public at large. Because an obligation always involves a commitment to another party, it follows that a management or board decision does not give rise to a constructive obligation at the balance sheet date unless the decision has been communicated before the balance sheet date to those affected by it in a sufficiently specific manner to raise a valid expectation in them that the enterprise will discharge its responsibilities.
21. An event that does not give rise to an obligation immediately may do so at a later date, because of changes in the law or because an act (for example, a sufficiently specific public statement) by the enterprise gives rise to a constructive obligation. For example, when environmental damage is caused there may be no obligation to remedy the consequences. However, the causing of the damage will become an obligating event when a new law requires the existing damage to be rectified or when the enterprise publicly accepts responsibility for rectification in a way that creates a constructive obligation.
22楼#
发布于:2012-02-02 17:08
22. Where details of a proposed new law have yet to be finalised, an obligation arises only when the legislation is virtually certain to be enacted as drafted. For the purpose of this Standard, such an obligation is treated as a legal obligation. Differences in circumstances surrounding enactment make it impossible to specify a single event that would make the enactment of a law virtually certain. In many cases it will be impossible to be virtually certain of the enactment of a law until it is enacted.
Probable Outflow of Resources Embodying Economic Benefits
23. For a liability to qualify for recognition there must be not only a present obligation but also the probability of an outflow of resources embodying economic benefits to settle that obligation. For the purpose of this Standard [3], an outflow of resources or other event is regarded as probable if the event is more likely than not to occur, i.e. the probability that the event will occur is greater than the probability that it will not. Where it is not probable that a present obligation exists, an enterprise discloses a contingent liability, unless the possibility of an outflow of resources embodying economic benefits is remote (see paragraph 86).
[3] The interpretation of 'probable' in this Standard as 'more likely than not' does not necessarily apply in other International Accounting Standards.
23楼#
发布于:2012-02-02 17:08
24. Where there are a number of similar obligations (e.g. product warranties or similar contracts) the probability that an outflow will be required in settlement is determined by considering the class of obligations as a whole. Although the likelihood of outflow for any one item may be small, it may well be probable that some outflow of resources will be needed to settle the class of obligations as a whole. If that is the case, a provision is recognised (if the other recognition criteria are met).
Reliable Estimate of the Obligation
25. The use of estimates is an essential part of the preparation of financial statements and does not undermine their reliability. This is especially true in the case of provisions, which by their nature are more uncertain than most other balance sheet items. Except in extremely rare cases, an enterprise will be able to determine a range of possible outcomes and can therefore make an estimate of the obligation that is sufficiently reliable to use in recognising a provision.
24楼#
发布于:2012-02-02 17:08
26. In the extremely rare case where no reliable estimate can be made, a liability exists that cannot be recognised. That liability is disclosed as a contingent liability (see paragraph 86).
Contingent Liabilities
27. An enterprise should not recognise a contingent liability.
28. A contingent liability is disclosed, as required by paragraph 86, unless the possibility of an outflow of resources embodying economic benefits is remote.
29. Where an enterprise is jointly and severally liable for an obligation, the part of the obligation that is expected to be met by other parties is treated as a contingent liability. The enterprise recognises a provision for the part of the obligation for which an outflow of resources embodying economic benefits is probable, except in the extremely rare circumstances where no reliable estimate can be made.
25楼#
发布于:2012-02-02 17:09
30. Contingent liabilities may develop in a way not initially expected. Therefore, they are assessed continually to determine whether an outflow of resources embodying economic benefits has become probable. If it becomes probable that an outflow of future economic benefits will be required for an item previously dealt with as a contingent liability, a provision is recognised in the financial statements of the period in which the change in probability occurs (except in the extremely rare circumstances where no reliable estimate can be made).
Contingent Assets
31. An enterprise should not recognise a contingent asset.
32. Contingent assets usually arise from unplanned or other unexpected events that give rise to the possibility of an inflow of economic benefits to the enterprise. An example is a claim that an enterprise is pursuing through legal processes, where the outcome is uncertain.
26楼#
发布于:2012-02-02 17:09
33. Contingent assets are not recognised in financial statements since this may result in the recognition of income that may never be realised. However, when the realisation of income is virtually certain, then the related asset is not a contingent asset and its recognition is appropriate.
34. A contingent asset is disclosed, as required by paragraph 89, where an inflow of economic benefits is probable.
35. Contingent assets are assessed continually to ensure that developments are appropriately reflected in the financial statements. If it has become virtually certain that an inflow of economic benefits will arise, the asset and the related income are recognised in the financial statements of the period in which the change occurs. If an inflow of economic benefits has become probable, an enterprise discloses the contingent asset (see paragraph 89).
27楼#
发布于:2012-02-02 17:09
Best Estimate
36. The amount recognised as a provision should be the best estimate of the expenditure required to settle the present obligation at the balance sheet date.
37. The best estimate of the expenditure required to settle the present obligation is the amount that an enterprise would rationally pay to settle the obligation at the balance sheet date or to transfer it to a third party at that time. It will often be impossible or prohibitively expensive to settle or transfer an obligation at the balance sheet date. However, the estimate of the amount that an enterprise would rationally pay to settle or transfer the obligation gives the best estimate of the expenditure required to settle the present obligation at the balance sheet date.
38. The estimates of outcome and financial effect are determined by the judgement of the management of the enterprise, supplemented by experience of similar transactions and, in some cases, reports from independent experts. The evidence considered includes any additional evidence provided by events after the balance sheet date.
28楼#
发布于:2012-02-02 17:09
39. Uncertainties surrounding the amount to be recognised as a provision are dealt with by various means according to the circumstances. Where the provision being measured involves a large population of items, the obligation is estimated by weighting all possible outcomes by their associated probabilities. The name for this statistical method of estimation is 'expected value'. The provision will therefore be different depending on whether the probability of a loss of a given amount is, for example, 60 per cent or 90 per cent. Where there is a continuous range of possible outcomes, and each point in that range is as likely as any other, the mid-point of the range is used.
Example
An enterprise sells goods with a warranty under which customers are covered for the cost of repairs of any manufacturing defects that become apparent within the first six months after purchase. If minor defects were detected in all products sold, repair costs of 1 million would result. If major defects were detected in all products sold, repair costs of 4 million would result. The enterprise's past experience and future expectations indicate that, for the coming year, 75 per cent of the goods sold will have no defects, 20 per cent of the goods sold will have minor defects and 5 per cent of the goods sold will have major defects. In accordance with paragraph 24, an enterprise assesses the probability of an outflow for the warranty obligations as a whole.
The expected value of the cost of repairs is:
(75% of nil) + (20% of 1m) + (5% of 4m) = 400,000
29楼#
发布于:2012-02-02 17:09
40. Where a single obligation is being measured, the individual most likely outcome may be the best estimate of the liability. However, even in such a case, the enterprise considers other possible outcomes. Where other possible outcomes are either mostly higher or mostly lower than the most likely outcome, the best estimate will be a higher or lower amount. For example, if an enterprise has to rectify a serious fault in a major plant that it has constructed for a customer, the individual most likely outcome may be for the repair to succeed at the first attempt at a cost of 1,000, but a provision for a larger amount is made if there is a significant chance that further attempts will be necessary.
41. The provision is measured before tax, as the tax consequences of the provision, and changes in it, are dealt with under IAS 12, Income Taxes.
Risks and Uncertainties

返回顶部